Rehabilition of the River Slea

The River Slea is an 18 mile long tributary of the River Witham, Lincolnshire. The River Slea is groundwater fed from Lincolnshire limestone aquifer and the flow depends on the on groundwater levels. Historically the River Slea flowed all year round. In the early 60s the flow of the river began to slow and ceased in 1962. This was due to a number of reasons such as over abstraction, increase in population and changes in weather cycles. After a public campaign in 1992, a pump was installed by the Environment Agency which delivers groundwater to the river at times of no flow. The Lincolnshire Rivers Trust (LRT) commissioned Clear Environmental to deliver the Sleaford Urban Opportunities Study, which was funded by Natural England. This study highlighted how the river would benefit from various rehabilitation techniques to enable wildlife to be more resilient during low flow periods and also contribute towards WFD objectives. With the help of the Wild Trout Trust, three sections of river were identified where restoration could be completed, this covered approximately 1.2km of river. Unfortunately, due to site constraints, work could only be completed on two sections (sections one and two). There were three phases to the works completed, these are detailed below;

 

Phase 1: Using an excavator, a low flow channel was created in section one and pools were created in section two. River bed material removed was used to create berms and meanders within the existing channel.

 

 

 

Phase 2: Brushwood bundles were installed, to construct berms which created pinch points, narrowing the channel to speed up the flow and maintain the pools created. This part of the project was made possible with the help of volunteers.

Phase 3: Planting of vegetation using coir matting and plug plants, to increase the rate of colonisation of berms and make them appear more natural.

We have already begun to see local benefits from the rehabilitation work we have carried out.  In September 2015, section one of the river was completely dry, but following the creation of the low flow channel, in September 2016 there was still 1ft of water retained within that section.

Before the works were completed, a water vole survey carried out in 2015 only found old unused burrows, with no signs of water voles. In 2016 another water vole survey was carried out, detecting 12 feeding stations and four latrines.

In 2015 section two was completely uniform with no pools or any habitat features. Following the work, 22 berms were constructed providing cover for fish and providing deeper areas that would help maintain the depth during low flow periods. Planting was successful, and in time, the vegetation will grow and create a natural meandering flow.

Since the work has been carried out Lincolnshire Rivers Trust have installed an interpretation board next to the river with the aim to educate passers-by about the rehabilitation work carried out, a guided walk event has also taken place to help engage with the local community and town council and more recently, Sleaford in Bloom awarded the Lincolnshire Rivers Trust acknowledging the work that has been carried out along the River Slea.

Thanks goes to Alan Partridge and Mr&Mrs Shimmin for the photographs that they have taken